LANGMUIR LABORATORY
OPERATION AND MAINTENANCE PLAN
May 1, 2001 - April 30, 2002
CIBOLA NATIONAL FOREST
MAGDALENA RANGER DISTRICT
Dennis R. Aldridge, Acting District Ranger, Approved 05/25/01
W. P. Winn, Chairman, Langmuir Laboratory, Approved 05/22/01
PLAN OBJECTIVES
The purpose of this annual plan is to provide close on-the-ground
coordination and management of the Langmuir Research Site as required in
the Special Use
Authorization, dated March 12, 1992, Clause 23.
MUTUAL AUTHORITIES
The Magdalena District Ranger or the designated Acting Magdalena
District Ranger is authorized to help prepare and approve the
Annual Operation and Maintenance Plan or amendment to the Plan.
The President of New Mexico Institute of Mining and Technology or
the Chairman of Langmuir Laboratory is authorized to help prepare
and approve the Annual Operation and Maintenance Plan or
amendments to the Plan.
An annual meeting of both parties will be scheduled by the
District Ranger at the convenience of both parties to provide the
coordination needed to prepare the Plan.
The Plan will be prepared by Langmuir Laboratory and approved by
all parties prior to the field season.
Amendments that are within the scope of the Operation and
Maintenance Plan may be submitted at any time for review and
approval of the other party. The maximum response time for
amendments by either party is 7 days; exceptions may be made if
additional information is needed.
SCHEDULE OF ACTIVITIES AND EXPERIMENTS
Preparations for summer experiments will begin in late May or early
June. No people are expected to be in residence at Langmuir
Laboratory (staying overnight) during the 2001 summer research
season. The active season will end around August 17, 2001. Laboratory
maintenance and winterizing will continue into October and perhaps
November, depending on weather.
The main research activities will include the following:
- An array of lightning rods will be installed near
South Baldy Peak and at other locations around Langmuir Laboratory
to study the zone of protection around the rods. Measurements of
lightning currents near South Baldy Peak will be conducted by personnel
from New Mexico Tech.
- Seismic activity will be monitored with an instrument located
just south of the Main Langmuir Building.
- The Long-Term Ecological Research Project will study
ground-dwelling arthropods, tree demography, and rodent populations.
- Instrumented balloons will be flown from the Balloon Hangar
for instrument testing.
- Instruments on two poles in the vicinity of the New Mexico
Tech Remote Observatory will be used to characterize turbulence
and its effect on telescope observations. One pole will be 30 feet high
and the other 45 feet high.
- A 14" diameter telescope on a tripod will be operated from
the Observatory.
- Chemists at New Mexico Tech will measure background levels
of ozone, NO$_{\rm x}$, hydrocarbons and carbonyl compounds in the
atmosphere, and similar compounds emitted from pine and fir trees.
- Trees and other fuel next to buildings are concerns which
will be addressed in cooperation with the District Ranger.
PERMANENT RESEARCH FACILITIES
Permanent research facilities include the following:
- Main Langmuir Building, Langmuir Annex, and A-Frame
Dormitory
- Socorro Electric Co-Op power line to the main buildings,
West Knoll, Balloon Hangar, and the Remote Observatory
- Water feed from Sawmill Canyon to the Main Langmuir
Building
- Two 150-kW diesel generators in quonset bunkers
- Storage yard, including trailers
- Supernova telescope facilities
- Instrument trailer at Microphone Hill
- Power and signal lines from the main buildings to West
Knoll, Balloon Hangar, Remote Observatory, and the Kivas
- Instrument trailer at West Knoll
- Rocket storage container, 7 by 2 by 2 feet. This box is
bullet proof and weighs about 3000 lbs. It is located near West
Knoll.
- Rocket Launching Pad near West Knoll (4 by 4 foot
concrete pad with three bolt studs to anchor launcher)
- Balloon Hangar and associated trailers
- Tracking radiosonde receiver near the Balloon Hangar
- New Mexico Tech Remote Observatory (formerly Joint
Observatory for Cometary Research)
- Rocket Launching and Instrument Platform north of Remote
Observatory
- Instrument Tower north of Remote Observatory
- Diesel Generator for Kivas in a small metal building. This
generator and its small building will be moved to a flat area above the
other generators near the main buildings.
- Kiva I and Kiva II---underground metal rooms for the study
of electromagnetic radiation from lightning and for triggering
lightning
- Areas designated for the long-term study of insect, rodent,
and plant populations and for the study of biomass production
- Miscellaneous instruments (rain gauges, electric field
meters, anemometers, etc.)
- Radar trailer to be located north of the Remote Observatory
- Other facilities not in the National Forest
NEW FACILITIES
Planning for the Magdalena Ridge Observatory, a major optical astronomy
observatory, will continue.
In addition, we are planning to build a second story onto part of
the existing Main Building for atmospheric research. Construction will
begin after plans, approvals, and funding are obtained.
ANTICIPATED TEMPORARY STRUCTURES
- Lightning rods near South Baldy Peak and at other locations
around Langmuir Laboratory.
- Two guyed poles will be installed near the Remote Observatory to
study turbulence. The towers will be 30 and 45 feet high. A small
building (7 by 7 by 8 feet) will remain near the southeast corner of
the Observatory to house instruments to record turbulence.
- Small stakes will be put in the ground to show where MRO
telescopes will be.
- [Amendment #1, dated 01/24/02:] Two temporary structures
will be placed in the saddle near the intersection of the minuteman cable
and the spur road to West Knoll. One structure is a transportable dome
with dimensions 12 x 22 x 16 feet. The other structure is a hut with
dimensions 5 x 8 x 6 feet. The dome will remain on a trailer during its
use and the hut will either remain on the back of a pickup truck or be
placed on blocks; there will be no permanent foundations. Power for the
operations will be taken from an existing power outlet nearby. Data will
be collected on nights with clear skies. Operations using these
structures will begin around January 28, 2002, and will continue through
April 30, 2002, which is the end of the current Operation and Maintenance
Plan. Further use will be addressed in the next operation and maintenance
plan.
SITE PLANS
The maps containing four sheets titled ``Topographic Orthophoto of
Langmuir Laboratory,'' dated 6/87, and related specifications
prepared by Langmuir Laboratory, are attached to and hereby made a
part of the Operation and Maintenance Plan.
MAINTENANCE SCHEDULE AND STANDARDS
Maintenance will be scheduled when it is required and it will
comply with the standards of New Mexico Tech and the USFS when
applicable.
Much of the downed cable across Sawmill Canyon has been removed; several
more pieces will be removed in September or October 2001.
SAFETY PROCEDURES
Langmuir Laboratory will adhere to Safety Procedures established by
New Mexico Tech. The Procedures include the following:
- Storing, transporting and launching of rockets will conform
to regulations of the Department of Defense and the Bureau of
Alcohol, Tobacco and Firearms.
- Restricted Area R5113 and the Tech and Withington Air
Traffic Control Assigned Airspaces (ATCAAs) will be operated in
accordance with a Letter of Agreement between New Mexico Tech and
the Federal Aviation Administration, Albuquerque Center.
- Before anticipated rocket firings, New Mexico Tech will
consult with the District Ranger, or his representative, to determine
fire danger rating. If fire danger is high or extreme, New Mexico
Tech will discuss risk of fire with the District Ranger and his staff
before deciding to launch missiles. The decision to launch rockets
lies with New Mexico Tech, which is responsible for prevention and
suppression of fires resulting from its activities, in accordance
with special use permit clause 28.
Additional safety procedures are established when 2.75-inch
rockets will be launched (not planned for 2001):
- The road to West Knoll will be blocked to vehicle traffic
whenever rockets are loaded in preparation for thunderstorm
investigations or test firings.
- The rocket landing area is the same one that we have used
for many years in the past; during 1994 we used only
that part of it south of the latitude of the Main Laboratory
Building.
- A description of the area, and how and when it will be used
will be published by New Mexico Tech in newspapers of local
distribution (notice attached).
- Warning signs (wording and map attached) will be posted at
the following locations if 2.75 inch diameter folding fin aircraft
rockets will be flown (not planned for 2001):
- Deer Plot Saddle on the old mining road
- Blue Cut (where Forest Road 235 crosses Timber Ridge)
- Both ends of Forest Trail 14 (where it joins Forest Roads
235 and 38)
- North end of Forest Trail 93 (where it joints Forest Road
235)
- Hardy Springs at the end of Forest Road 47
- The high-altitude end of Forest Trail 11 (South Baldy Crossing)
- The south end of Forest Trail 8 (where it meets Forest Road 235)
- Where Forest Trail 17 (Ryan Hill Canyon) crosses the Forest
Boundary
- Before each anticipated firing, New Mexico Tech will be
reasonably secure in the fact that people are not within the
impact area. Determination will also be made through the District
Ranger that fire crews or other Forest personnel are not within
the impact area.
- All grazing and special use permittees affected by the
impact areas will be notified in writing by new Mexico Tech of the
coming summer program. Copies of the notification letters will be
furnished to the District Ranger. The Ranger will furnish a list
of permittees involved.
- Rocket landing areas will be observed for a full 48-hour
period after each launch to determine if fires may have been
started by rockets.
- Property liability insurance will be carried by New Mexico
Tech to adequately cover the hazards of the operation.
PUBLIC ACCESS AND VEHICLE RESTRICTIONS
When New Mexico Tech employees are in residence at the Laboratory,
the public will be allowed access to the first floor of the Main
Laboratory Building, which houses the kitchen and dining areas,
bathrooms, visitor center, and main data collecting area. The
public may also be guided into other areas by a Volunteer Host
or by employees of New Mexico Tech.
The Forest Service will provide signs for the Langmuir Research
Site boundary at major road and trail routes.
Off-road vehicle use is prohibited within the Langmuir Research
Site, except on roads.
Special Order #03-67 closes the Principal Research Area as shown
on map dated October 22, 1990, JRL, to ultra-light aircraft and
hang-gliders except by permit of the Forest Supervisor.
EROSION CONTROL
Road damage from erosion will be repaired as needed.
OFF-SEASON CLOSURE PROCEDURES
The main gate will be closed whenever there are too few employees to
keep the main buildings under surveillance. We anticipate that the main
gate will be open only on an irregular basis in July and August 2001.
VISITOR INFORMATION
Information will be available at the Main Laboratory Building.