The date is: Fri Jan 29 11:10:06 MST 1999 1/29/99 This week we briefly discussed the pros and cons of different chassis design. Tracked was goin to be simple yet difficult. We decided to canabalize parts from an old RC and use a mechanical differential that would enable us to drive both rear wheels while using only one motor for the task. We also discussed an alternate base of balsa wood (light, strong, and conducts no noise). Ultimately we decided on a modified Ackerman(sp?) setup but would use all sets of wheels to turn. Next Week we hopefully will be able to iron out the mechanical specifics of implementing the ackerman setup as well as maybe get our hands on some sensors and begin testing with those to see how we need to plan. We also will need to difinitivly(sp?) decide on who is going to what on the project. Another than that, we'll see. The date is: Fri Feb 5 14:28:46 MST 1999 This week we went a little further as far as chassis fabrication only to find out that we didn't know exactly what dimensions we wanted to use. We decided on at least the width of the differential we have and a minimum length that is as long as the battery. This is just a starting point and can be flushed out from there. Greg came up with a program flow chart that would work but may need details added here and there. This weekend some supplies will be picked up in Albuquerque that will be needed. Next week we hope to have some sensors to play with, if they come in. I have also considered the possibility of purchasing some alternative sensors on the group budget, but this is only and idea. Ultrasonic detectors are a bit expensive, but not outside the budget of $100. We hope to have the chassis laid out next week and some preliminary work with the sensors and the control program. Back to the grindstone. The date is: Fri Feb 12 13:24:05 MST 1999 This week we were unsuccesfull in attempting to get get the robot chassis dynamics working. I.E. I was unable to get parts in ABQ and thus we have to wait till next week to begin that phase. The 2D12 sensors came in this week and we began preliminary tests on the wall sensors. We also placed and order for 4 more of the 2D12's for applications in wall sensing and similar functions. The motor controller was also tested and a method of operation of the motor was determined. Some of the others have come up with a preliminary diagram of program flow yet I have actually to see this. Next week we hope to have whose duty is what firmly established(finally) and to begin testing of the robot chassis by remote control to test the feasibility of the modified Ackerman method. Wall sensor testings will continue as well. I hope to come up with an alternate fire extinguishing method. Perhaps compressed CO2 or something similar. Ideas will flourish from there. Progress continues.... The date is: Fri Feb 26 13:25:39 MST 1999 This week while in explanation was uneventful, is still somewhat packed. Last weekend, using my father's milling machine, I fabricated new arpieces out of aluminum that would provide an actual "bolt on" arm instead of jurry-rigging some old parts with washers and such. Also, I obtained new pieces for the steering linkage as well. While the task was succesful I was not happy with how they worked overall. So this weekend I plan on fabricating some new pieces as well as creating mounts for the servo. With all the slop taken out of the linkage I will focus on the wheels as they are the last place that has significant play. I also researched getting electrically actuated valves. The men at the machine shop helped me out by giving me data books and letting me look at a sample of what one of the valves looks like. The name on the catalog escapes me at the moment but the other company that makes such devices is called minimatic (mini-pneumatics) and are located in Albuquerque. I will get ahold of them next week. Early progress was slow, the group needs to pick up the pace. The date is: Fri Mar 5 11:32:47 MST 1999 Dr. Wedeward, I successfully recreated new arm pieces in which to mount the front wheel spindles. However, this week had it's difficulties in implementing the steering of our ackerman setup. At first there was too much play in the linkage that allowed the servo to turn without actually making much impact as to the angle of the wheels. Greater stability was achieved through tighter allthread and some new hardware on which to mount the steering pivots. The last task in the front wheels is to add some bearings take out the remaining slop. Once this is done it should be a pretty tight system. As far as steering goes. The rear section implementation is up for next week's project. I was unable to get ahold of minimatics this week to procure some valves for the CO2 fire suppression system. I believe I am going to switch to my backup plan of a simple fan and then if I can get ahold of some stuff to implement the CO2 then I may give that a try. Progress continues... The date is: Wed Mar 17 18:02:32 MST 1999 This report is for the last week before spring break. Sorry it's late but i guess better late than never. In complete truth, I accomplished very little this week. Being the knuckle head that I am I forgot to purchase sensors in ABQ one weekend and had to go back on Tuesday afternoon so my productivity there was pretty much shot. I did however begin inital tests of the fire-putter-outer system. We got a fan from radio shack and decided that it would not meet our needs. We instead opted for a different mottor with a seperate fan. Tests continue with that. I am going to explore an optional method of putting the flame out, I just need to check the rules on something. Progress gains momentum. Sorry for the lateness of this report. The date is: Fri Apr 9 13:27:22 MDT 1999 Well, since one set of reports got wiped out and I forgot to do last week's report I'm going to try to do a grand summation of what I've done for a while. Finally got the mechanics of te rear steering worked out and it works quite well. I fabricated a second layer out of aluminum and modified the chassis to accomodate stays that would hold up the next level. Then even more levels were added using simple perfboard. These will be used to keep the robot from being top heavy. We finally got a fire suppression system working. A really _POWERFUL_ fan. It could knock the flame out from the end of the room if we had to. With the chassis being pretty much complete I moved on to learning how to use PC Boards to do wire-traces for the sensor boards. While this is easy to say, I've spent the last couple of lab sessions gleaning tips from others and generally teaching how to use it and PSpice myself. Other than that progress continues more rapidly now. -Sorry, I accidentally sent a message under the title NONAME The date is: Fri Apr 23 08:30:13 MDT 1999 The first half of this week was spent working on the printed circuit boards. I cut and etched boards for the wall and white line sensors, pwm, and the main power board with a big fat ground on it. That pretty much ate up 3-4 hours of my time on Tuesday. And on Thursday I was pretty useless. I didn't have any boards to etch and powers and grounds on the robot were being worked together by Clint. The only thing I have to do is mount the white line sensor when Nate finishes up with it. The date is: Fri May 7 14:07:09 MDT 1999 Dr. Wedeward, This will be my final report on Glitchy the fire fighter. This week it very much a collabrative effort to get Glitchy up to par for his final inspection Thursday. So instead of describing what I specifically did, I'll just summaraze what the group did. For this week we needed to spiffy Glitchy up and turn him into a more robust design. To do this we removed all the old perfboard and put in its place, nicely cut pieces of lexan. In doing this we also widened the levels so that we need only two and not three. The circuit board layers were consolodated by connecting each board via metal stans to another piece of lexan. with the battery layer the second layer, we needed the batteries to be secure. To do this we used high density foam rubber and it seems to work well and not allow the batteries to shift at all. Sensors mounted, attachments made glitchy was it his final state of construction for the moment. Over the course of the summer Glitcy will see improvements with the addition of his fire sensor and fire suppression. Who knows, other, new ideas may be incorporated as well.